How long does a DOCA kitchen take?
There is no honest universal week count. Cabinet production time is not the same as total renovation time, and any figure given before technical approval is a planning range rather than a date.
A project moves through discovery, cabinet planning, field and technical coordination, approval and production release, production in Spain, site preparation, cabinet installation, and adjacent finishes and closeout. Permitting, demolition, utilities, structural work, flooring, surfaces, appliances and inspections may sit on entirely different schedules. Five things move the date more than anything else: appliance decisions, field conditions, unassigned scope boundaries, surface fabrication and site access.
What should I ask for instead of a delivery date?
Ask for the current project-specific sequence, the assumptions behind it, what has not yet been verified, and which events can change the date.
Treat any early timing as a planning range until technical approval and production release. A schedule becomes credible at the point where every owner, every input and every approval is visible, which is a different moment from the point where someone first says a number. This is worth asking of any showroom, not only this one.
What happens at the first consultation, and does it cost anything?
The first consultation is complimentary. It is a working session to establish what is already decided, what is still open, and whether a showroom visit, a material review or a project conversation is the useful next step.
Plans are useful but not required. The intake asks about project direction and timing so the Brookline team can prepare for the right first conversation rather than starting from a blank page. Expect questions about what is changing in the kitchen, whether it is part of a larger renovation, where the home is, who else is already involved, and who besides you will be part of choosing the kitchen.
What do you need from me before cabinetry can be ordered?
Verified field dimensions, a settled appliance schedule and an approved set of cabinet documents. Production is released against approved drawings, not against intent.
Major appliances and their current installation requirements should be resolved first, because cabinet panels, clearances, ventilation, electrical and water connections are model-specific. Field verification confirms dimensions and identifies which walls, floors, utilities, appliances, surfaces and cabinet interfaces belong to which member of the project team. Releasing cabinets before those inputs are reliable usually creates more delay than waiting for correct information.
Does DOCA Boston install the cabinetry?
DOCA Boston has an installation team on staff, so design and installation can stay under one roof. What installation covers on a given project is confirmed in the project agreement.
The installation scope is the DOCA package: setting, aligning and adjusting the cabinetry, then documenting product punch items. It does not extend to the construction around it. Surfaces, appliances, electrical, plumbing and the other trades stay with the project team assigned to them, and writing that split down before anyone starts is worth the ten minutes it takes.